Intersection improvement – Sturgeon Road & Range Road 250 Roundabout

Project Description

The Project

A Sturgeon County contractor will be building a roundabout on Sturgeon Road and Range Road 250. This project is intended to improve the flow of traffic and improve safety for those using the intersection

Project Scope

The construction will require the realignment of the existing road. This work will address the flow of traffic through the intersection and improve safety for the public.

Please be aware that construction schedules may change depending on weather conditions.

What this Means to You

We expect that the project will take about eight weeks to complete.

Related Documents

 

 

Updates

  • September 24, 2024: Project underway
    September 24, 2024

    Construction is underway on the southern portion of the roundabout.

  • August 21, 2024: Updated start date
    August 21, 2024

    The contractor has indicated that they will begin work on this project on Monday, August 26.

  • August 6, 2024: Traffic delays
    August 6, 2024

    There will be traffic delays as the contractor moves equipment to the site.

  • August 1, 2024
    August 1, 2024

    Fortis is on-site, traffic delays are expected during construction.

  • July 29, 2024: Tentative Start
    July 29, 2024

    Tentative start date is July 29, Fortis will be on site completing the removal of existing streetlights and poles.

  • July 19, 2024: Expected start date
    July 19, 2024

    Work on the project is still expected to start in late July.

  • June 25, 2024: Start date
    June 25, 2024

    The contract has been awarded. It is expected that construction will begin in late July.

  • June 6, 2024: Resident letter added
    June 6, 2024

    The letter to residents is available in the Related Documents section.

Newsletter

Subscribe for direct news and project updates to your inbox.

Connect

Scroll to Top