Intersection improvement – Sturgeon Road & Range Road 250 Roundabout

Project Description

The Project

A Sturgeon County contractor will be building a roundabout on Sturgeon Road and Range Road 250. This project is intended to improve the flow of traffic and improve safety for those using the intersection

Project Scope

The construction will require the realignment of the existing road. This work will address the flow of traffic through the intersection and improve safety for the public.

Please be aware that construction schedules may change depending on weather conditions.

What this Means to You

We expect that the project will take about eight weeks to complete.

Related Documents

 

Updates

  • November 27, 2024: Seasonal Shutdown
    November 27, 2024

    Any remaining work on this project will be done in the spring.

  • November 8, 2024: Paving
    November 8, 2024

    The paving is expected to wrap up by the week of November 12, with site clean up to follow. New street lights are scheduled to be installed next month

  • November 1, 2024: Paving next week
    November 1, 2024

    The concrete work is expected to be done next week allowing the paving to start. Streetlights will be installed in December 2024.

  • October 25, 2024: Work continues
    October 25, 2024

    Crews continue to work on this project. While we don’t have a specific update this week, we will keep you informed as this project progresses.

  • October 18, 2024: Concrete
    October 18, 2024

    Drivers should expect changes in traffic patters during the coming weeks during the concrete work. That should take about two weeks to complete, depending on the weather conditions.

  • October 10, 2024: Concrete
    October 10, 2024

    Drivers should expect changes in traffic patterns in the coming weeks when construction crews start the cement work.

  • September 24, 2024: Project underway
    September 24, 2024

    Construction is underway on the southern portion of the roundabout.

  • August 21, 2024: Updated start date
    August 21, 2024

    The contractor has indicated that they will begin work on this project on Monday, August 26.

  • August 6, 2024: Traffic delays
    August 6, 2024

    There will be traffic delays as the contractor moves equipment to the site.

  • August 1, 2024
    August 1, 2024

    Fortis is on-site, traffic delays are expected during construction.

  • July 29, 2024: Tentative Start
    July 29, 2024

    Tentative start date is July 29, Fortis will be on site completing the removal of existing streetlights and poles.

  • July 19, 2024: Expected start date
    July 19, 2024

    Work on the project is still expected to start in late July.

  • June 25, 2024: Start date
    June 25, 2024

    The contract has been awarded. It is expected that construction will begin in late July.

  • June 6, 2024: Resident letter added
    June 6, 2024

    The letter to residents is available in the Related Documents section.

Newsletter

Subscribe for direct news and project updates to your inbox.

Connect

Scroll to Top