- Project category: Safety
- Division: Division 1
- Status: In progress
Project Description
The Project
A Sturgeon County contractor will be building a roundabout on Sturgeon Road and Range Road 250. This project is intended to improve the flow of traffic and improve safety for those using the intersection
Project Scope
The construction will require the realignment of the existing road. This work will address the flow of traffic through the intersection and improve safety for the public.
Please be aware that construction schedules may change depending on weather conditions.
What this Means to You
We expect that the project will take about eight weeks to complete.
Related Documents
Updates
-
November 27, 2024: Seasonal ShutdownNovember 27, 2024
Any remaining work on this project will be done in the spring.
-
November 8, 2024: PavingNovember 8, 2024
The paving is expected to wrap up by the week of November 12, with site clean up to follow. New street lights are scheduled to be installed next month
-
November 1, 2024: Paving next weekNovember 1, 2024
The concrete work is expected to be done next week allowing the paving to start. Streetlights will be installed in December 2024.
-
October 25, 2024: Work continuesOctober 25, 2024
Crews continue to work on this project. While we don’t have a specific update this week, we will keep you informed as this project progresses.
-
October 18, 2024: ConcreteOctober 18, 2024
Drivers should expect changes in traffic patters during the coming weeks during the concrete work. That should take about two weeks to complete, depending on the weather conditions.
-
October 10, 2024: ConcreteOctober 10, 2024
Drivers should expect changes in traffic patterns in the coming weeks when construction crews start the cement work.
-
September 24, 2024: Project underwaySeptember 24, 2024
Construction is underway on the southern portion of the roundabout.
-
August 21, 2024: Updated start dateAugust 21, 2024
The contractor has indicated that they will begin work on this project on Monday, August 26.
-
August 6, 2024: Traffic delaysAugust 6, 2024
There will be traffic delays as the contractor moves equipment to the site.
-
August 1, 2024August 1, 2024
Fortis is on-site, traffic delays are expected during construction.
-
July 29, 2024: Tentative StartJuly 29, 2024
Tentative start date is July 29, Fortis will be on site completing the removal of existing streetlights and poles.
-
July 19, 2024: Expected start dateJuly 19, 2024
Work on the project is still expected to start in late July.
-
June 25, 2024: Start dateJune 25, 2024
The contract has been awarded. It is expected that construction will begin in late July.
-
June 6, 2024: Resident letter addedJune 6, 2024
The letter to residents is available in the Related Documents section.
Newsletter
Subscribe for direct news and project updates to your inbox.