Range Road 220 at Township Road 570

Project Description

The Project

Pavement repair work will be done starting at the intersection of Range Road 220 and Township Road 570 extending to the north access of Juniper Subdivision and inside Juniper Subdivision, beginning at the intersection of Range Road 220 and Township Road 570, extending to the northern project limit.

What this Means to You

One lane will be closed while the work is being done during the week. Traffic signs will be in place. It is expected the work will continue until May 24, weather permitting.

 

Map

Updates

  • November 27, 2024: Seasonal shutdown
    November 27, 2024

    Any remaining work on this project will be completed in the spring.

  • November, 8 2024: Work continues
    November 8, 2024

    Work will continue as long as the conditions allow.

  • November 1, 2024: Topsoil
    November 1, 2024

    Topsoil is being spread over the project area, this should take another seven to 10 days.

  • October 25, 2024: Work continues
    October 25, 2024

    Work continues on this project. While we don’t have any specific updates this week, we will keep you informed as this project progresses.

  • October 18, 2024: Topsoil
    October 18, 2024

    Topsoil is scheduled to be added along Range Road 220 and within the subdivision in the next two weeks. Weather permitting, the project could wrap up by the end of October.

  • October 11, 2024: Project update
    October 11, 2024

    The construction crews are steadily working on this project. While there are no specific updates this week, we will keep you informed as the project progresses.

  • August 2, 2024
    August 2, 2024

    The work is scheduled to start on Wednesday, August 7, and is expected to be completed by Saturday, August 10, 2024, weather permitting.

    During this time, one lane will be temporarily closed while the repairs are being carried out.

  • May 10, 2024: Work update
    May 10, 2024

    The pavement repair work is now underway.

Newsletter

Subscribe for direct news and project updates to your inbox.

Connect

Scroll to Top