- Project category: Paved Roads
- Division: Division 5
- Status: In progress
Project Description
A Sturgeon County contractor, Central Civil Solutions, will be working on rehabilitating the subdivision roads in Woodridge. This project will upgrade the existing roads from gravel to a paved surface. Central Civil Solutions will deliver a notice of construction to the nearby residents in advance of construction.
Project Scope
The work will involve roadway reconstruction, granular base, asphalt paving, ditch work, culvert installations, clearing, and landscaping. The work will begin in Meadow Crescent and Woodridge Crescent, then move to Erickson Drive.
What this Means to You
Minor detours will be required throughout the project affecting the normal movement of traffic and pedestrians. During this time, there will be numerous personnel including subcontractors and heavy equipment in the construction zone. Please obey flaggers, detours, barricades, and traffic signs and drive safely through the area. Typical working hours are from 7 a.m. to 7 p.m. with long weekends off.
Related Documents
Updates
-
November 27, 2024: Seasonal shutdownNovember 27, 2024
The core project is done, but the contractor will return in the spring to finish landscaping.
-
November 8, 2024: Winter shutdownNovember 8, 2024
Due to the colder temperatures, the remaining work will be done next spring.
-
November 1, 2024: Winter preparationsNovember 1, 2024
The contractor will continue to shape the ditches and prep the site for winter. Due to the colder temperatures, the remaining work will be done next spring.
-
October 25, 2024: Project updateOctober 25, 2024
The construction crews are steadily working on this project. While there are no specific updates this week, we will keep you informed as these projects progress.
-
October 18, 2024: PavingOctober 18, 2024
The bottom lift of asphalt on Erickson Drive (west) and Meadow Crescent is done. Grading and GBC placement on Erickson Drive (east) will be done by the end of this week, with paving to happen this weekend. Top soil will be added in the ditches.
-
October 11, 2024: Project updateOctober 11, 2024
Paving on Erickson Drive (from the west project limit to Range Road 233) and Meadow Crescent is ongoing. Grading and gravel placement for the east section of Erickson Drive will be done early next week with paving to follow once Meadow Crescent is done.
Topsoil placement, seeding, and general site clean up will continue until the end of October.
-
September 24, 2024: Completion dateSeptember 24, 2024
The project completion date is now mid to late October, weather permitting.
Paving will continue on Woodridge Crescent while grade widening and gravel placement will take place on Meadow Crescent and Erickson Drive.
-
September 6, 2024: PavingSeptember 6, 2024
The gravel haul on Woodridge Crescent is scheduled to be done this week, with the bottom lift of paving set to begin next week.
-
August 16, 2024: Grade widening & culvertsAugust 16, 2024
Grade widening on Woodridge and Meadow Crescent is ongoing. The contractor continues to work on culvert replacements, and the final lift of material is being placed before the gravel is placed.
-
August 6, 2024: Grade wideningAugust 6, 2024
Construction crews are still working to increase the width of the road surface.
-
July 19, 2024: Grade wideningJuly 19, 2024
Grade widening within Woodridge and Meadow Crescent is ongoing. The contractor will start hauling in material to bring the road back to grade.
-
June 26, 2024: Construction underwayJune 26, 2024
Construction has started on this project. The contractor is currently stropping topsoil from Meadow Crescent.
-
June 12, 2024: Start date announcedJune 12, 2024
Construction is scheduled to start on June 17 and will last until mid-September, depending on the weather. The contractor is Central Civil Solutions. They will be distributing a notice of construction over the next few days.
-