Woodridge subdivision

Project Description

A Sturgeon County contractor, Central Civil Solutions, will be working on rehabilitating the subdivision roads in Woodridge. This project will upgrade the existing roads from gravel to a paved surface. Central Civil Solutions will deliver a notice of construction to the nearby residents in advance of construction.

Project Scope

The work will involve roadway reconstruction, granular base, asphalt paving, ditch work, culvert installations, clearing, and landscaping. The work will begin in Meadow Crescent and Woodridge Crescent, then move to Erickson Drive.

What this Means to You

Minor detours will be required throughout the project affecting the normal movement of traffic and pedestrians. During this time, there will be numerous personnel including subcontractors and heavy equipment in the construction zone. Please obey flaggers, detours, barricades, and traffic signs and drive safely through the area. Typical working hours are from 7 a.m. to 7 p.m. with long weekends off.

Related Documents

Map

Updates

  • September 24, 2024: Completion date
    September 24, 2024

    The project completion date is now mid to late October, weather permitting.

    Paving will continue on Woodridge Crescent while grade widening and gravel placement will take place on Meadow Crescent and Erickson Drive.

  • September 6, 2024: Paving
    September 6, 2024

    The gravel haul on Woodridge Crescent is scheduled to be done this week, with the bottom lift of paving set to begin next week.

     

  • August 16, 2024: Grade widening & culverts
    August 16, 2024

    Grade widening on Woodridge and Meadow Crescent is ongoing. The contractor continues to work on culvert replacements, and the final lift of material is being placed before the gravel is placed.

  • August 6, 2024: Grade widening
    August 6, 2024

    Construction crews are still working to increase the width of the road surface.

  • July 19, 2024: Grade widening
    July 19, 2024

    Grade widening within Woodridge and Meadow Crescent is ongoing. The contractor will start hauling in material to bring the road back to grade.

  • June 26, 2024: Construction underway
    June 26, 2024

    Construction has started on this project. The contractor is currently stropping topsoil from Meadow Crescent.

  • June 12, 2024: Start date announced
    June 12, 2024

    Construction is scheduled to start on June 17 and will last until mid-September, depending on the weather. The contractor is Central Civil Solutions. They will be distributing a notice of construction over the next few days.

  • March 6, 2024: Project page created
    March 6, 2024

No results found.

Newsletter

Subscribe for direct news and project updates to your inbox.

Connect

Sturgeon County offices will be closed for Monday, October 14. County offices and facilities will re-open Tuesday, October 15 for regular business hours 8:30AM - 4:30PM.

Scroll to Top