Construction Update – January 2023

Transport Crews:

  • Finished their portion of the areas west of Villeneuve.
  • Transport cable placed from Glory Hills to Rosal Acres and then from Hwy 779 down to Westwood Lane.
  • Splicing is happening in the peds and handholes between Villeneuve and Calahoo.

Access Crews:

  • Finished the areas west of Villeneuve (except Pine Sands).

Drop Crews:

  • Working in areas west of Villeneuve, finishing up Calahoo, Shil-shol, and Rosal Acres.
  • Cable between Calahoo and Shil shol has been placed and is being spliced. Crews will begin pulling cable from Calahoo up past Dover Estates. Cable is installed from Villeneuve to Calahoo and is scheduled for power up at the end of the month.

Other:

  • CFOC is working with our first “live” resident, this resident was a beta test resident in the Villeneuve area.; once they have the beta customer up and running 100%, they will begin installing ONTs in Villeneuve.