Construction Updates – February 25, 2024

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • A small portion of the Pro North area is still to be completed.

Drop fibre (connects the access fibre to the premise)

  • Drops will continue in the remaining areas when ground conditions allow it.
  • Most of the drops left require pipeline crossing agreements and special installation procedures.

Splicing (connecting the fiber segments into one continuous length)

  • Splicing along the mainline between Villeneuve and Highway 642 is complete.
  • Meadowview Drive area is complete.
  • Crews are working along Township Road 554 and Riviere Qui Barre.

ONT installation (the last step before service is available to a premise)

  • ONT installations are being scheduled in Heritage I.P, Pro North I.P, Transport between Villeneuve and Highway 642, and Terrault Estates.