Construction Updates – March 10, 2024

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Crews are on site at Pro North assessing the last pipeline crossing there and should have this section wrapped up shortly.
  • All other access construction is complete.

Drop fibre (connects the access fibre to the premise)

  • Drops will continue in the remaining areas when the ground conditions allow it.
  • Most of the drops left require pipeline crossing agreements and special installation procedures.

Splicing (connecting the fiber segments into one continuous length)

  • Splicing is complete except for the last crossing in Pro North and one pedestal in Northern Lights, which will be completed next week.
  • All other splicing is complete.

ONT installation (the last step before service is available to a premise)

  • 56 ONT installations are currently scheduled. More are being booked all over the east side of the project.