Construction Updates – March 17, 2024

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • A crew is currently working on site at Pro North to finish the last section of access construction.
  • All other access construction is complete.

Drop fibre (connects the access fibre to the premise)

  • Drops will continue in the remaining areas when the ground conditions allow it.
  • Most of the drops left require pipeline crossing agreements and special installation procedures.

Splicing (connecting the fiber segments into one continuous length)

  • Splicing and the cable pull at Northern Lights has been completed.
  • Splicing is complete except for the last crossing in Pro North.
  • All other splicing is complete.

ONT installation (the last step before service is available to a premise)

  • ONT installations are being booked in all areas east of Villeneuve

#SturgeonCounty offices will be operating with reduced hours May 15, to accommodate a staff training event. Offices will re-open from 10:30 AM - 4:30 PM.

A fire restriction is in effect for Sturgeon County and the towns of Bon Accord, Legal and Redwater.

Scroll to Top