Construction Updates – November 2023

Transport Fibre (connects subdivisions, hamlets and industrial parks together)

  • T4 (Highway 633, Range Road 262, Highway 37, Township Road 544): one pipeline crossing left to do near Pro North; all cable is pulled except that section.
  • T7 (Meadowview Drive): the last transport section left to do in phase 1 and it is currently being plowed. Road crossings are complete, tie-ins and handholes still to install there.

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Pro North is approximately 95 per cent complete; two pipeline crossings left to do.
  • Willow Rose Mobile Home Park is complete.

Drop fibre (connects the access fibre to the premise)

  • Crews working on the east side of Villeneuve.
  • There are two drops left to do in the Fairhavens.

Splicing (connecting the fiber segments into one continuous length)

  • Working from Deb’s heading south along Range Road 255 and towards Riviere Qui Barre.
  • Range Road 262 is currently being spliced, crews will move to Willow Rose Mobile Home Park.