Construction Updates – October 2023

Transport Fibre (connects subdivisions, hamlets and industrial parks together)

  • T4 (Highway 633, Range Road 262, Highway 37, Township Road 544: cable is currently being pulled. Approx. 60% complete.
  • T5 (Range Road 255 & Highway 642): Cable is pulled, just a pipeline crossing left to do.
  • T6 (Township Road 544 & Range Road 262): Cable is pulled, just a pipeline crossing left to do.
  • T7 (Meadowview Drive): ploughing has only a few kilometers left to complete.

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Pro North started last week and is 65% done.
  • Willow Rose Mobile Home Park will start in the next few weeks.

Drop fibre (connects the access fibre to the premise)

  • Locates were called in and drops have been completed in Willow Rose Mobile Home Park.
  • Villeneuve Airport and West Fairhaven are complete.
  • Fairhaven – we are working on a pipeline crossing there.
  • West Villeneuve – should be completed in the next few weeks.
  • T2 (Calahoo to Pine Sands) is 85% done.
  • Heritage I.P. is 70% done
  • Silver Chief will be done this week. This crew will move to Reyda Vista next week.

Splicing (connecting the fiber segments into one continuous length)

  • Silver Chief is 45% done.
  • Will be working on T4 and T5 transport segment and Range Road 262 over the next couple of weeks.