Construction Updates – September 2023

Transport Fibre (connects subdivisions, hamlets and industrial parks together)

  • Range Road 255 up to Highway 642 and Township Road 554 into Riviere Qui Barre are almost complete.
  • The highway segments east of Villeneuve are being worked on. Handholes and tie-ins are being finished up.
  • Crews will be down on Meadowview Drive after the Villeneuve east segments are completed.

Access Fibre (runs by each premise in a subdivision, hamlet or industrial park)

  • Fairhaven and West Fairhaven are 98% done.
  • Reyda Vista and the Airport are complete.
  • Silver Chief was started in late September, and is 45% complete.

Drop fibre (connects the access fibre to the premise)

  • Glory Hills is complete.
  • Riviere Qui Barre is 98% done
  • Fairhavens are 75% done.
  • Range Road 262 is 85% done.
  • Airport was started on Sept 18. It is currently 30% complete.
  • Heritage I.P., Northern Lights and Reyda Vista will be the next communities (in that order).

Splicing (connecting the fiber segments into one continuous length)

  • Transport section 2, going into Pine Sands is complete
  • Airport is complete, this area just requires drops.
  • Riviere Qui Barre, Reyda Vista and Heritage I.P are complete.
  • Fairhavens are 35% complete.

Sturgeon County offices will be closed for Monday, October 14. County offices and facilities will re-open Tuesday, October 15 for regular business hours 8:30AM - 4:30PM.

Scroll to Top