Construction Updates – September 6, 2024

Drop fibre (connects the access fiber to the premise)

  • All drops are completed besides the ones requiring pipeline agreements.
  • Pipeline agreements are awaiting fully executed ATCO agreements.

ONT installation (the last step before service is available to a premise)

  • Once your drop installation is complete, you are ready to contact Canadian Fibre Optics Corporation to have your Optical Network Terminal (ONT) installed and activated, 1-888-236-2947

Remediation work is ongoing in areas where it has been identified as required.

A fire restriction is in effect for Sturgeon County and the towns of Bon Accord, Legal and Redwater as of May 21, 2025.

 

Learn about the resources available to those affected by the Redwater Rec Area fire.

Scroll to Top